The Island Resort and Casino’s $33 million expansion moved to phase two of construction. The expanded building is now completely enclosed and heated. Instead of using steel, the resort chose to use pre-cast concrete – saving quite a bit of time.
“They put it up from start to finish in three months. So, we’re in closed, it’s warm, there’s heat in here, the guys can work all winter,” said Tony Mancilla, general manager of the Island Resort and Casino.
Phase one – constructing the outside of the building – was completed mid-December. The crew is now on phase two.
“Phase two is going to take roughly six months. It’s all the Ruffins – mechanical, electrical, plumbing, fire suppression, metal studs.” Said Peter Dupuis, project manager from Gundlach Champion.