The Heartland’s newest casino project is taking shape and the dice could be rolling at Walker’s Bluff as soon as next year.
The framework for the hotel and casino is up and roadways are almost completed out onto the property. Roadways, which were an issue before, are now being widened and worked on to get out to the property.
“Currently, the south section and the north section, the earth end embankment is all completed. A lot of the curb and gutters are in place, all the drainage structures are in place,” said Travis Emery, Williamson County Highway Engineer.
Emery tells me the roadways are about 65 percent complete.